RMP Sample Exam 3

RMP Sample Exam 3

1 / 50

During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites. The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process.

What should the project manager do next?

2 / 50

While creating the appropriate risk strategy, the project manager discovers that the project team lacks the necessary expertise to define the risk management plan. There is no time to initiate immediate training, but training will be provided before releasing the team.

What should the project manager do to address the knowledge gap?

3 / 50

The risk manager of a medium-sized project is performing risk response planning with the project team. The proposed action for one specific, primary risk introduces a secondary risk.

What should the risk manager and the risk owner of the primary risk do about this situation?

4 / 50

When considering human factors of risk management, a project manager is concerned that a few members of the organization have the power to greatly influence risk attitudes relative to the risk process at individual and group levels. This could cause sudden shifts in organizational risk attitudes based on the personal perceptions and interests of only a few people.

What should the project manager do to manage the influence these individuals have on the risk management process?

5 / 50

A project team is preparing for an upcoming project and has identified project risks and developed risk response strategies to address risks should they materialize. What should the project team do next before finalizing the risk response planning process?

6 / 50

The engineering department offers the project manager some highly skilled resources for the same cost as those currently on the project team. What should the project manager do next to handle this situation?

7 / 50

Company A sells a new machine to Company B. During the risk assessment, the stakeholders of Company A do not want the risk of transporting the machine from their facility. Instead, they want Company B to take responsibility and liability once the machine leaves Company A’s facility.
What strategy is Company A using to deal with the risk?

8 / 50

The senior risk manager hears that critical deliverables are delayed because a key subject matter expert (SME) does not have enough time to allocate to the tasks. The risk manager sees this as an opportunity to coach the project manager.

What should the risk manager review with the project manager?

9 / 50

A cost analyst team member asks the project manager for the latest risk data for inclusion with the cost estimates for the project. Which tool should the cost analyst team member use to identify the probability of achieving specific cost targets?

 

10 / 50

You are managing a large infrastructure project that involves multiple stakeholders and high technical uncertainty. During a recent risk review meeting, a critical supplier flagged a potential delay in delivering key components due to regulatory issues in their country. You realize this could significantly impact your project timeline.

You had previously identified this type of risk during planning but categorized it as “low impact” based on initial information. However, now with new data, the impact appears to be high. Your sponsor is asking for a proactive risk handling plan.

What should you do next?

11 / 50

A risk is identified early in the project. After six months, it is determined that the risk does not apply to this particular project. How should the risk be handled by the risk manager?

12 / 50

In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to project cancellation.

How should the probability and impact be characterized for this risk?

13 / 50

During a progress meeting, the project team learns that an identified risk materialized. The project manager decides to execute the risk response plan, but the contingency reserve does not cover the total budget for that plan.
What should the project manager do?

14 / 50

A risk response strategy was not appropriately implemented leading to substantial budget and schedule issues. It was discovered that a risk action owner was never assigned to the risk.

When should the project manager have assigned a risk action owner?

15 / 50

A risk manager is coaching a team on risk management best practices. The team believes that monitoring risks is only necessary while a risk response strategy is being implemented. The project manager explains that the team should be more proactive when monitoring risks. What should the risk manager instruct the team to do in order to proactively monitor risks?

16 / 50

A project team is working on a complex project, but they are having trouble planning risk management for the project due to a lack of specific knowledge within a technical domain. The project manager would like to hire an external risk manager with specific technical expertise to assist in identifying and analyzing risks.

What should the project manager do?

17 / 50

After applying several risk identification techniques, the risk manager is ready to document project risks in the risk register, including risk name, risk statement, probability of occurring, and potential impact.

After this information is documented, who should typically be designated as the risk owner(s)?

18 / 50

A pharmaceutical company undertakes a new, year-long research and development (R&D) project. The company pursues high margins on investments and an aggressive growth strategy. They maintain a central program management office (PMO) to assist with new projects and record data on past project performance. The company leadership regularly makes decisions regarding the full suite of company projects and requires comparative data and reports. Project leadership is well-versed in risk management and the PMO requires full documentation of project management artifacts.

Based on the characteristics of this new project, what is the level of stakeholder risk appetite and appropriate risk strategy?

19 / 50

A project manager is creating a risk management plan, but participants in a group meeting are hesitant to express their concerns and opinions.

What should the project manager do to ensure that they capture everyone’s opinions?

20 / 50

The risk manager joins a project team that is planning for a new project and realizes that no risk management activities have been initiated. The team is operating under the assumption that, since the stakeholders have worked on high-risk projects in the past, they are highly tolerant of uncertainty. The risk manager insists that they confirm stakeholder risk appetite before moving forward.

What should the risk manager do first to help define stakeholder risk appetite?

21 / 50

risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance.

Which aspect of risk impact should be prioritized when designing the risk impact scale?

22 / 50

A risk-seeking organization has experienced measurable success based on its current strategy for growth. While planning for a new project, the team discovers that overall project risk far exceeds the risk threshold for the organization. The team presents their findings to stakeholders and senior management.

What should the project manager suggest?

23 / 50

The sponsor hires a project manager as a consultant to evaluate a change program currently underway. The change program manager tells the consultant that the program, currently in the execution phase, is in good standing and detailed plans are complete and available for review. After reviewing the project documentation and talking to stakeholders, the consultant finds that this is not true. Detailed resource plans do not exist, the risk register has not been updated for months, and contract negotiations with a key vendor are behind schedule for critical deliverables.

What is the first action the consulting project manager should take based on the current state of the project?

24 / 50

A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes no major risks threaten the schedule, budget, or quality. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization’s risk appetite is low.

What is the first step that should be taken?

25 / 50

The risk manager is prioritizing risks based on the potential impact on cost and schedule and identifies the following four risks:

Risk 1 has a US$500,000 potential cost increase, and a 60-day potential schedule slippage, with a 25% probability of occurring.

 

Risk 2 has a US$200,000 potential cost increase, and a 20-day potential schedule slippage, with a 60% probability of occurring.

 

Risk 3 has a US$1,200,000 potential cost increase, and a 90-day potential schedule slippage, with a 10% probability of occurring.

 

Risk 4 has a US$600,000 potential cost increase, and a 70-day potential schedule slippage, with a 20% probability of occurring.

 

Using expected monetary value (EMV) calculation, which risk has the greatest potential impact on cost and schedule?

26 / 50

A project risk manager participated in a project risk assessment for a struggling project and reviewed the final results. What should the project risk manager do next to increase the likelihood of project success?

27 / 50

The project enters a testing phase to validate a project requirement. The testing is occurring in a common company testing area maintained by operations. The project team accepts the external customer’s additional testing requirements, which may cause a slip in the schedule. A risk is identified, added to the risk register, and a response is developed.

What is the next step?

28 / 50

During a company’s audit, it is found that no risk management information exists within the lessons learned database. What could the company do to increase the amount of risk management organizational process assets?

29 / 50

A company is executing a high-visibility project to develop mobile phone technology. The project sponsor is concerned that an overall high-risk rating may undermine support for the project within the company. The sponsor has instructed the project manager to manipulate the data used for the Monte Carlo simulation to artificially reduce the risk rating.

What should the project manager do?

30 / 50

During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer’s electrical infrastructure. This event was not originally identified as a risk. To maintain the project schedule, the project manager decides to purchase a new power adapter.

What type of response best describes this course of action?

31 / 50

You’re managing a high-risk project. Your stakeholders are demanding frequent risk updates. What should you do to manage their expectations?

32 / 50

Your project team discovers a previously unidentified risk during execution. What should you do first?

33 / 50

You’ve identified a risk that would cause minor schedule delays, and the cost to respond to it exceeds the potential impact. What is the best response?

34 / 50

During a project risk review, a stakeholder informs you of a regulation change that could impact your project’s schedule and cost. What should you do first?

35 / 50

You are managing a project where a key supplier has shown signs of potential bankruptcy. To handle this risk, you decide to enter into a contract with another supplier who can take over in case the current supplier fails. What type of risk response strategy are you using?

36 / 50

Question

A project team is conducting initial risk planning and is seeking to identify a framework against which identified risks can be assessed during initial risk management planning and throughout the project life-cycle.

What should the project team do at this stage to determine the appropriate assessment framework?

37 / 50

Question

Halfway into the development of a new product, previously unidentified risks are emerging frequently. The project team was unprepared for these risks and must develop response strategies as the risks arise. This is causing delays and disorder.

What should the project manager do?

38 / 50

A project’s outcome is highly sensitive to and dependent upon financial market activity. Therefore, the project’s budget was planned using a conservative scenario with high exchange-rate variations. The company’s financial advisor delivers daily exchange-rate forecasts to the project team. The financial advisor informs the project manager that an upcoming scenario could induce extremely high exchange rate variations.

What should the project manager do?

39 / 50

A project is nearing completion when the risk manager learns that a change in market regulations may impact the project. The project manager is unsure how to proceed.

What should the risk manager do?

40 / 50

A looming fuel price increase was identified as a risk during the planning stages of a large construction project. The identified risk was assigned high probability with low impact; the price increase would not be more than 2%. Shortly after the project begins, a 20% fuel price increase goes into effect.

What should the project manager do?

41 / 50

A project manager at a private aerospace company is working on a complex state-of-the-art project that is a top priority for the company. The project will have a high degree of uncertainty and will be subject to strict regulatory and compliance requirements. Just before the project is scheduled to begin, the project team identifies a new risk introduced by a pending change in government regulations.

What should the project manager do to proactively ensure effective project risk management?

42 / 50

A team member suggests adding a task that is outside of the baseline scope. This task could reduce risk to a critical component of the project.

What should the project risk manager do?

43 / 50

A project manager is concerned about the low performance of risk management on a mission-critical project. After assessing the situation, the risk manager finds that the team is not communicating effectively. The project manager has met with the team and established communication protocols to address the issue.

What should the project manager do to continue to influence team members to improve performance?

44 / 50

A project has many high-probability risks associated with several key deliverables. What tactic should the risk manager emphasize as critical and mandatory while monitoring project risks?

45 / 50

Question

A company is about to start a project in a remote location known for extreme weather. The agreed-upon approach was to implement the project using a predicted, multiphase approach. Each phase is composed of several iterations.

What should the risk manager do in the event of extreme weather?

46 / 50

A team member in a hybrid organization informs the project manager of a new way to execute an activity with a shorter duration. The project manager has not used the new process before, but a trusted team member explains that their previous experience with the process validates the efficacy of the new process.

What should the project manager do?

47 / 50

An agile team created a risk register for a project. All initial risks were identified using stakeholder interviews, workshops, and information from the project charter. What should the project manager do to manage the risk register and the associated risks for the remaining project duration?

48 / 50

A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated.

From which of the following sources should the funds be drawn to cover the risk mitigation?

49 / 50

A formal analysis is completed on a major change to a research and development (R&D) program at a risk-averse corporation. This analysis includes a detailed review of the risk exposure and funds required to take appropriate actions. The risks included cost, labor, materials, and traveling to the facilities. Within the entire project portfolio, management only has US$995,000 for R&D projects.

The inclusive, detailed breakout of budget analysis is as follows:

Material Cost: Labor Costs: Travel Costs:
Optimistic US$ 550,000 US$ 125,000 US$ 40,000
Most Likely US$ 650,000 US$ 250,000 US$ 150,000
Pessimistic US$ 700,000 US$ 400,000 US$ 175,000

What should the risk manager propose to the review board as a recommendation based on the information above?

50 / 50

A project risk manager must complete a report for a stakeholder who is extremely concerned about the possibility of a funding shortfall. The stakeholder believes that funding shortages have the highest risk exposure and should be ranked as the highest risk.

Threat / Opportunity Probability Impact
Funding shortage 1 5
Materials delivery 2 4
Labor shortage 3 2
Schedule slippage 5 2
Delayed procurement 3 5
New technology 3 3
1 = Very Low 2 = Low 3 = Moderate 4 = High 5 = Very High

What is the most important element to communicate this to the stakeholder to provide a more accurate understanding of the overall risk exposure of the project?

Your score is

0%

For more Sample papers, refer the links below: