RMP Sample Exam 2

RMP Sample Exam 2

1 / 50

A risk manager calls a meeting to identify risks for a technically complicated volatile project. The meeting will be attended by the project team, key stakeholders, and several subject matter experts (SMEs) invited by the project manager. Some stakeholders expressed concern over the number of attendees and questioned the inclusion of the SMEs.

What should the risk manager say to explain the importance of including the SMEs?

2 / 50

Upon returning from an extended vacation, the risk manager observed during the project status meeting that several activities being accomplished were not in the original plan and may introduce additional risk. The team is attending a conference and will return to the office in two days.

What should the risk manager do first?

3 / 50

In the planning stage of an upgrade project, a project manager benchmarked other recent projects that use the same technology. The project manager discovered that longer-than-planned outages occurred in most cases due to frequent maintenance activities.

What will be the project manager’s next step?

4 / 50

A risk has been identified in a multi-functional project, but the project manager decides to take no action. A stakeholder complains that the project manager did not respond to the risk and is concerned about the project as a result. The project manager arranged a meeting to discuss this concern and describe response strategies, specifically the strategy used in this situation.

What type of response strategy should the project manager be sure to explain and clarify to the stakeholder?

5 / 50

While preparing for a new project, the risk manager discovers that there is a lot of uncertainty associated with the project, and trade-offs that will affect different objectives may be necessary.

What qualitative risk analysis method will be the most helpful in determining the relative weighting of the project’s objectives in terms of their priority to the stakeholders?

 

6 / 50

During the execution phase at the customer’s worksite, an issue arises when new parts don’t fit properly into a machine. The site project manager believes that this was a high probability risk but cannot find it in the risk register. The site project manager confronts the risk manager demanding an explanation.

What should the risk manager do?

7 / 50

A project risk manager is working with the project team to establish risk metrics that must be tracked for a new technology project.

What metrics are best suited for this purpose?

8 / 50

A project risk manager schedules a third workshop to facilitate the qualitative risk analysis. One team member complains that they should not have iterative meetings, because they should complete this at the beginning of the project.

Which of the following should the project risk manager do?

9 / 50

During a project team meeting, team members are identifying risks that may occur during the project. What type of analysis should the risk manager perform in preparation for a meeting with the sponsor?

10 / 50

During iteration planning, a risk manager discusses user stories with the team. While prioritizing the user stories, it was discovered that some high-value stories were also identified as having greater risks.

What should the risk manager do?

11 / 50

A risk manager joins an ongoing project and realizes that the risk identification process was cut short and there are potential risks that may not have been identified or planned for. The risk manager raises the issue with stakeholders but they are not concerned. The stakeholders explained that there were timeline constraints and assured the risk manager that they captured the risks with the highest probability of occurrence and largest impacts.

How should the risk manager address this situation?

12 / 50

A risk manager is notified that the supplier responsible for implementing component changes for a reporting system is unlikely to meet the project schedule deadline. Based on the risk response plan, the risk manager secured stakeholder approval to use paper forms until the component changes go live. It is still possible, however, that the paper form changes may not be ready in time.

Which risk type is the risk manager facing in this situation?

13 / 50

While creating a risk management plan, the project manager is informed that the project sponsor has instructed the project team to focus solely on financial risks because they are the only risks to the project.

How should the project manager proceed?

14 / 50

For quality assurance, a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available.

What should the project manager highlight when explaining why an attendance list important?

15 / 50

A CEO wants to reduce the time spent on risk management activities. The risk manager opposes this decision but is overruled. The project team follows orders to move on to other project planning activities.

What should the risk manager have done to avoid this situation?

16 / 50

After the kickoff meeting for an industrial project, the assigned risk manager must lead the team in identifying project risks. As team members are distributed across six countries, which risk identification method is preferable in this situation?

17 / 50

A construction project is underway to build a new office building. The project team has identified several risks related to the project, including delays in material delivery, changes in building codes, and unexpected weather conditions. The team has developed a contingency plan to address these risks, but they need to identify trigger conditions that will activate the plan.

What should the team do in order to complete this task?

18 / 50

The project team is implementing a computer interface to facilitate communications between two ticketing systems for two major companies in the IT industry. While planning risk responses, the project team agrees on a contingency plan that should mitigate the negative impact of the risk. However, during project execution, one of the subject matter experts identified a residual risk that was not considered during the risk response planning session that could potentially affect the project schedule baseline.

What should the risk manager do to handle this residual risk?

19 / 50

A risk manager is managing the build of an off-shore data center and is the custodian of the assets procured by the project. The risk manager is informed by a team member that an asset was lost, and the team member is ready to pay for the missing asset.

How should the project manager handle this situation?

20 / 50

A new project is initiated to develop several new financial products and services for a company with offices in several countries. The risk manager has researched the regulations for each of the countries. Based on the research, the risk manager is concerned that some new products and services do not offer enough protection for the consumer.

What should the risk manager do first?

21 / 50

While performing a qualitative project risk analysis process the risk manager finds that the product is missing the “Definition of Done”.

What type of risk is this?

22 / 50

A six-month, US$1.2 million project is two months into implementation. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project’s reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones.

Based on this project data, what technique should the risk manager recommend to improve the risk management process?

23 / 50

A technology project has members of a project team from multiple countries. The stakeholders have stated that this arrangement will keep the project within budget. However, the risk manager believes that the stakeholders have not accounted for issues that might arise that could affect the success of the project.

What should the risk manager do to record this concern?

 

24 / 50

The project manager requests a method to analyze risk data in a simple format. What format should the risk manager suggest for the preliminary review of the data?

25 / 50

Question

A new team member is added to the project team from a matrix organization. The project is unique within the organization and has a high level of risk associated with it.

How should the project’s risk manager familiarize the new team member with the project’s risk management process?

26 / 50

A risk manager and the project team identified risks, performed a qualitative risk analysis, and prepared a risk response plan. However, delays in the response to risk events are affecting the project schedule.

How would assigning risk owners to the risk responses help avoid these delays?

 

27 / 50

Question

A project manager is preparing for a meeting with the chief executive officer (CEO) to present the project’s master schedule of the critical path. One hour before the meeting, the project manager receives a report from an off-shore team documenting newly identified significant risks associated with a critical milestone in the development and quality testing standards of off-shore production activities. Based on this information, the project manager realizes the master schedule is no longer realistic.

What should the project manager do?

28 / 50

During a retrospective meeting, the project team confirmed that all deliverables were completed according to the specifications provided in the product backlog. However, the number of errors found during testing increased dramatically.

What should the project manager do?

29 / 50

During a project review meeting, an executive scrutinizes the risk section, including risks on the watch list, and demands action to close them out. What is the executive’s risk attitude?

30 / 50

During the construction of an infrastructure improvement project, several risks have materialized and require immediate mitigation efforts. To optimize response effectiveness, the risk manager wants to leverage monitoring processes to gather data about these active risks.

Which of the following actions would be relevant and valuable in leveraging monitoring processes to gather data about these active risks?

31 / 50

During a status meeting, a team member alerts the project manager that the delivery timeline for a component prototype is unattainable due to the unanticipated complexity of the requirements. After confirming the impending delay, the project manager must take action to address the situation.

How should the project manager address this issue?

32 / 50

Which of the following techniques for planning risk response can provide a means of identifying symptoms for use as trigger conditions for contingency responses?

33 / 50

A project manager wants to represent the distribution of uncertainty around a risk model element. However, good data on the variability of the risk model element has not been collected and only contains minimum and maximum values.

What curve should the project manager use to represent the distribution?

34 / 50

A risk manager is working on a new project for which historical data is not available. The risk manager planned to use historical data to identify potential risks and develop appropriate risk response strategies.

What should the project manager do next?

35 / 50

The opening of a new overseas office faces potential delays as the required permit has not yet been issued by the local government. The project team met to evaluate the appropriate course of action as outlined in the risk register. After a thorough assessment, the team decided to postpone the opening to another date.

Which document should the project manager use to update the project management plan?

36 / 50

While reviewing preliminary project information the project manager discovers that, based on the organizational business drivers, there is an opportunity to increase the value of the project outcome. In order to exploit this opportunity the organization must invest in a new technology.

How should the project manager justify this investment when presenting this information to senior management?

37 / 50

A risk manager is planning for a new project but is running into resistance while attempting to manage stakeholder expectations. One key stakeholder is refusing to acknowledge the reality of several project risks and requests that the risk manager disregard those risks.

What should the risk manager do?

38 / 50

A project manager is assigned to a two-month project with three project team members. The project sponsor tells the project manager to skip any risk planning activities because risk management is not necessary for such a small project.

How should the project manager respond?

39 / 50

An organization has a low threshold for risk and is concerned about initiating a project that has an elevated level of uncertainty associated with the local economy. All other identified risks are within the organization’s risk tolerance parameters. Management would like to initiate the project but before moving forward they require a better understanding of the risks and how they contribute to overall project risk. The project manager is creating a report to present to senior management in order to determine whether or not the project should be initiated.

What should the project manager do to provide additional clarity and facilitate informed decision-making?

40 / 50

At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project.

What risk management process improvement should the risk manager recommend for future similar projects?

41 / 50

A risk manager is presenting the risk management plan for a high-priority project to senior management and organizational executives. The project is cutting-edge and part of a completely new strategy for the organization. A majority of the management team is excited about the potential opportunities that the project presents, but some high-priority leadership team members are not comfortable taking on the risk and expense associated with the project. During the presentation, it was clear the groups of stakeholders did not agree on the appropriate organizational risk appetite which has led to conflict.

How can the risk manager lead conflict resolutions between stakeholders in agreeing on risk appetite?

42 / 50

A project team must incorporate newly identified risks into the risk management framework. Stakeholders would like an update on which risks would have the highest impact on the project.

What should the project team do?

43 / 50

A project manager identifies a risk in a multifunctional project and decides to take no action to address it. What should the risk manager do if the risk occurs and has a negative impact on the project?

 

44 / 50

A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.

What is the most effective method to capture these opportunities?

45 / 50

Question

A risk manager on a large-scale development project has established detailed risk management procedures. The risk manager wants to ensure their effectiveness and is refining the risk monitoring practices to better track, record, and assess execution success.

What metric would be most valuable to track and record the execution quality of risk-related procedures?

46 / 50

After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.

What forecasting methodology should the project manager request be utilized to calculate the impact?

47 / 50

Question

A risk manager is working with an experienced project team on a complex project. During production, a risk materializes and the team meets to discuss the implementation of the appropriate risk response strategy. Despite planning risk responses as a team, the risk manager notices that many of the team members seem extremely uncomfortable and are reluctant to implement the risk response.

What should the risk manager have done in order to better understand how the team would react in this situation?

48 / 50

Question

A project team is working on a critical project and one of the identified risks is approaching its risk threshold. This risk introduces potential delays due to unexpected changes in requirements.

Who is ultimately responsible for monitoring the risk that is about to exceed its risk threshold?

The original project manager should have identified high-level risks and risk responses in the project planning phase. Identifying high-level risks and responses in the project planning phase can help to ensure that potential risks are identified and addressed before they become issues. This can help to mitigate risks and ensure that appropriate risk response strategies are in place to address any issues that may arise.

49 / 50

A project manager has just taken over an ongoing project from another project manager. During a review of the project management plan, the new project manager realizes that the cost variance and schedule variance are largely negative. Several reported issues have not been resolved, vendors have not been paid for work done, and risk mitigation is quickly depleting the budget.

Which action should the original project manager have taken to avoid this situation?

50 / 50

A risk manager has finished a qualitative risk analysis with their team. The risk manager asked the team to update the relevant documents, but they only updated the risk register, issue log, and risk report. Which project document still needs to be updated based on this information?

 

Your score is

0%

For more Sample papers, refer the links below: