RMP Sample Exam 2 RMP Sample Exam 2 1 / 50 A risk manager calls a meeting to identify risks for a technically complicated volatile project. The meeting will be attended by the project team, key stakeholders, and several subject matter experts (SMEs) invited by the project manager. Some stakeholders expressed concern over the number of attendees and questioned the inclusion of the SMEs. What should the risk manager say to explain the importance of including the SMEs? Subject matter experts have specialized expertise and can help identify and address high-risk issues. Identifying risks in a meeting with subject matter experts makes it easier to get better resources for the project. Risks will be easier to accept if the subject matter experts who attended the meeting work together. The subject matter experts will provide ongoing support if they are included early in the planning process. Subject matter experts have specialized knowledge and experience in their respective fields, which can be invaluable in identifying and addressing high-risk issues in a technically complicated project. By including SMEs in the risk identification process, the risk manager can ensure that all potential risks are identified and that the project team has access to the best possible information and expertise to manage those risks effectively. This can ultimately lead to a more successful project outcome. 2 / 50 Upon returning from an extended vacation, the risk manager observed during the project status meeting that several activities being accomplished were not in the original plan and may introduce additional risk. The team is attending a conference and will return to the office in two days. What should the risk manager do first? Meet with the project team. Report the out-of-scope work. Examine activities for new risks. Review the change control log. The risk manager should first review the change control log to understand how the out-of-scope work was approved and whether it was properly documented and communicated to the project team. This will help the risk manager understand the impact of the out-of-scope work on the project and identify any potential new risks that may have been introduced. It is important to proactively manage risks to minimize their impact and ensure project success. 3 / 50 In the planning stage of an upgrade project, a project manager benchmarked other recent projects that use the same technology. The project manager discovered that longer-than-planned outages occurred in most cases due to frequent maintenance activities. What will be the project manager’s next step? Benchmark projects using other technologies to establish a more objective baseline. Compare other similar technologies and recommend the implementation of another technology. Create a risk item in the risk register and incorporate the thresholds according to the benchmarks. Discuss the probable downtime with the sponsor and obtain approval for outages. The project manager should create a risk item in the risk register and incorporate the thresholds according to the benchmarks. By doing so, the project manager can proactively identify and manage the risks associated with longer-than-planned outages due to frequent maintenance activities. This can help minimize the impact of these risks on the project and ensure its success. 4 / 50 A risk has been identified in a multi-functional project, but the project manager decides to take no action. A stakeholder complains that the project manager did not respond to the risk and is concerned about the project as a result. The project manager arranged a meeting to discuss this concern and describe response strategies, specifically the strategy used in this situation. What type of response strategy should the project manager be sure to explain and clarify to the stakeholder? Avoidance Exploitation Procrastination Acceptance When a risk has been identified and the project manager decides to take no action, this is considered a risk acceptance response. Risk acceptance is a risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs. This strategy may be appropriate for low-priority threats, and it may also be adopted where it is not possible or cost-effective to address a threat in any other way. 5 / 50 While preparing for a new project, the risk manager discovers that there is a lot of uncertainty associated with the project, and trade-offs that will affect different objectives may be necessary. What qualitative risk analysis method will be the most helpful in determining the relative weighting of the project’s objectives in terms of their priority to the stakeholders? Expected Monetary Value (EMV) Root-Cause Analysis Decision Tree Analysis Analytic hierarchy process (AHP) The most helpful qualitative risk analysis method in determining the relative weighting of the project’s objectives in terms of their priority to the stakeholders is the analytic hierarchy process (AHP). AHP is a structured and systematic approach that helps to prioritize and make decisions based on multiple criteria. It involves breaking down complex decisions into smaller, more manageable parts and comparing them using a set of criteria. AHP results are weights (summing to 100%) that reflect the relative priority of each objective. This prioritization can be important in determining how trade-offs affecting different objectives (e.g., Should we reduce scope to finish on time?) will be decided. 6 / 50 During the execution phase at the customer’s worksite, an issue arises when new parts don’t fit properly into a machine. The site project manager believes that this was a high probability risk but cannot find it in the risk register. The site project manager confronts the risk manager demanding an explanation. What should the risk manager do? Apologize to the site manager, take full responsibility for the oversight, and promise to address the issue immediately. Determine whether the issue was logged in the register or was overlooked during the risk identification process. Inform the site project manager that the risk of new parts not fitting properly into the machine is a low probability risk. Arrange a meeting with the site project manager to discuss why they did not communicate the risk adequately. In this situation, the risk manager should determine whether the issue was logged in the risk register or was overlooked during the risk identification process. If the risk was not included in the risk register, the risk manager should investigate why it was missed and take steps to prevent similar issues from occurring in the future. Additionally, the risk manager should assess the impact of the risk on the project objectives, schedule, and budget, and develop a risk response plan that outlines the steps to be taken to mitigate the risk. Finally, the risk manager should communicate the new risk and response plan to all relevant stakeholders, including the project team, project sponsors, and the customer. 7 / 50 A project risk manager is working with the project team to establish risk metrics that must be tracked for a new technology project. What metrics are best suited for this purpose? Efficacy of the work breakdown structure. Number of approved change requests. Number of defects identified. Effectiveness of response plans. As a project risk manager, it is important to establish risk metrics that can help identify potential risks and measure the quality of project deliverables. This metric can be used to measure the quality of the project deliverables and identify potential risks that may impact the project’s success. It is important to select metrics that are relevant to the project and can provide meaningful insights into potential risks. Tracking the number of defects provides insights into the performance and stability of the new technology being developed. 8 / 50 A project risk manager schedules a third workshop to facilitate the qualitative risk analysis. One team member complains that they should not have iterative meetings, because they should complete this at the beginning of the project. Which of the following should the project risk manager do? Continue with the workshop, but discipline the team member for undermining the authority of the project manager. Agree with the team member, as qualitative analysis should only be performed during the initial stages of a project. Proceed with the meeting and remove the team member from the list of attendees for future meetings. Explain that it is good practice to perform qualitative analysis throughout the life of the project. It is good practice to perform qualitative analysis throughout the life of the project, not just at the beginning. This is because risks can change and new risks can emerge throughout the project, and it is important to continuously monitor and analyze them. The project manager should explain this to the team member who complained and emphasize the importance of ongoing risk analysis. 9 / 50 During a project team meeting, team members are identifying risks that may occur during the project. What type of analysis should the risk manager perform in preparation for a meeting with the sponsor? Qualitative risk analysis. Quantitative risk analysis. Monte Carlo risk analysis. Expert judgment analysis. Qualitative risk analysis is the consideration of a range of characteristics such as the probability of occurrence, degree of impact on the objectives, manageability, timing of possible impacts, relationships with other risks, and common causes or effects. Multiple types of analysis are used to determine risk, but at this stage of the project, qualitative risk analysis is most appropriate for the project manager to perform in preparation for a meeting with the sponsor. The team members are identifying risks, not analyzing previously identified risks. Quantitative risk analysis examines the combined effect of identified risks on the desired outcome. A Monte Carlo risk analysis is a technique that computes or iterates the project cost or project schedule many times using input values, selected at random from probability distributions of possible costs or durations, to calculate a distribution of possible total project cost or completion dates. Expert judgment could help to identify some risks but may be subject to biases and may only offer limited perspective. Therefore, the correct answer is qualitative risk analysis. 10 / 50 During iteration planning, a risk manager discusses user stories with the team. While prioritizing the user stories, it was discovered that some high-value stories were also identified as having greater risks. What should the risk manager do? Suggest that the stories with higher risk are included in the earlier sprints instead of the later ones. Recommend that the stories with lower risk are included in the earlier sprints to increase team motivation. Work with the product stakeholders to schedule which user stories should be worked on in which sprints. Conduct a Monte Carlo analysis to identify which user stories should be completed first. When prioritizing user stories during iteration planning, if high-value stories are also identified as having greater risks, the risk manager should suggest that these stories be included in the earlier sprints instead of the later ones. Work that is unique, significant, risky, or novel can be prioritized to reduce the uncertainty associated with project scope at the start of the project before a significant investment has taken place. This approach allows the team to address the higher-risk stories earlier in the project, which can help to mitigate potential issues and reduce overall project risk. 11 / 50 A risk manager joins an ongoing project and realizes that the risk identification process was cut short and there are potential risks that may not have been identified or planned for. The risk manager raises the issue with stakeholders but they are not concerned. The stakeholders explained that there were timeline constraints and assured the risk manager that they captured the risks with the highest probability of occurrence and largest impacts. How should the risk manager address this situation? Advise that the team revisit the risk identification process despite the time constraints. Document the explanations provided by the stakeholders and continue as planned. Ensure that all of the high probability and impact risks have response strategies. Request to be reassigned to another project that has not initiated planning activities. The risk manager should advise the team to revisit the risk identification process despite the time constraints. This will ensure that all potential risks are identified and planned for, which is essential for effective risk management. Failing to identify and plan for all potential risks in a project can have severe consequences. If potential risks are not identified and planned for, they may materialize during the project and cause delays, cost overruns, or other issues that can ultimately lead to project failure. Unidentified risks may require additional resources or unplanned expenditures to address, which can increase project costs and significantly impact the project timeline. Not identifying and planning for all potential risks in a project can lead to an increased likelihood of decreased quality, damage to reputation, and legal or regulatory issues. 12 / 50 A risk manager is notified that the supplier responsible for implementing component changes for a reporting system is unlikely to meet the project schedule deadline. Based on the risk response plan, the risk manager secured stakeholder approval to use paper forms until the component changes go live. It is still possible, however, that the paper form changes may not be ready in time. Which risk type is the risk manager facing in this situation? Secondary risk Residual risk Primary risk Compliance risk The risk manager in this situation is facing a residual risk. A residual risk is a risk that remains after risk response planning has been completed, and it is typically managed through contingency plans. In this case, the risk manager has identified the primary risk of the supplier not meeting the project schedule and has implemented a risk response plan by using paper forms as a contingency. However, there is still a possibility that the paper form changes may not be ready in time, which represents a residual risk. It is important for the risk manager to continue monitoring and managing this risk to minimize its impact on the project. 13 / 50 While creating a risk management plan, the project manager is informed that the project sponsor has instructed the project team to focus solely on financial risks because they are the only risks to the project. How should the project manager proceed? Instruct the team to continue creating the risk management plan focusing solely on financial project risks as the project sponsor mandated. Demand that the project team identify and assess all project risks immediately and tell them to disregard similar requests moving forward. Escalate the issue to senior management because the sponsor is incorrect and ignoring additional risks puts the entire project at risk. Meet with the sponsor and use historical data and enterprise environmental factors to demonstrate that other risk types are relevant. Focusing solely on financial risks may put the entire project at risk as other risks may also impact the project. The project manager should coach the project sponsor and demonstrate that is important to identify and assess all project risks to ensure that the project is successful. Enterprise environmental factors (EEFs) are internal and external environmental factors that surround or influence project success. EEFs such as organizational culture, industry standards, marketplace conditions, and legal and regulatory requirements introduce various types of risks and must be evaluated. Using historical project information can also be a useful tool for demonstrating the relevance of other risk types. By analyzing past projects, the project manager can identify risks that may not have been considered before and use this information to inform the risk management plan. The project manager can use data and evidence to support their reasoning and convince the sponsor to consider other risk types. Coaching the project sponsor can help ensure that the project is successful by providing support, guidance, and clarity around expectations and risk management practices. 14 / 50 For quality assurance, a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available. What should the project manager highlight when explaining why an attendance list important? It is a document that is registered within the lessons learned register. It is a record that shows the number of attendees in the meeting. It is standard practice on projects to conduct risk review meetings, however meeting attendance may be optional. The attendance list is evidence that risk review meetings were held with the appropriate project team members. Risk review meetings should be held regularly and attended by appropriate team members as they can contribute adequately to risk identification, assessment, and mitigation. An attendance list is important because it serves as evidence that risk review meetings were held with the appropriate project team members. This is important for ensuring that all necessary stakeholders are involved in the risk management process and that decisions are made with the appropriate input. 15 / 50 A CEO wants to reduce the time spent on risk management activities. The risk manager opposes this decision but is overruled. The project team follows orders to move on to other project planning activities. What should the risk manager have done to avoid this situation? Instructed the CEO to attend risk management meetings. Decreased the overall number of project risks identified. Communicated the outputs and value of risk management. Explained the importance of a generous planning schedule. The risk manager should have communicated the outputs and value of risk management to the CEO in order to demonstrate the importance of the risk management activities. This would have helped the CEO understand the benefits of risk management and the potential negative consequences of reducing the time spent on it. By effectively communicating the value of risk management, the risk manager could have potentially convinced the CEO to reconsider their decision. 16 / 50 After the kickoff meeting for an industrial project, the assigned risk manager must lead the team in identifying project risks. As team members are distributed across six countries, which risk identification method is preferable in this situation? Affinity diagram Decision tree analysis The Delphi technique Monte Carlo analysis In this situation, the Delphi technique is the best risk identification method to use. This technique uses a facilitated anonymous polling of subject matter experts to identify risks in their area of expertise. The facilitator gathers the experts’ initial responses and circulates them without attribution to the entire group. The group members may then revise their contributions based on those of others. The process often generates a consensus of the experts after a few iterations. This approach is particularly useful when team members are not co-located and may have different perspectives on the project risks. 17 / 50 A construction project is underway to build a new office building. The project team has identified several risks related to the project, including delays in material delivery, changes in building codes, and unexpected weather conditions. The team has developed a contingency plan to address these risks, but they need to identify trigger conditions that will activate the plan. What should the team do in order to complete this task? Identify symptoms that indicate that a risk is about to occur or has already occurred. Pinpoint gaps in information, areas of miscommunication, or additional requirements. Track the rate at which project activities are completed within predefined intervals. Compile an exhaustive list of all stakeholders impacted by implementing contingency plans. To complete the task of identifying trigger conditions that will activate the contingency plan, the project team should identify symptoms that indicate that a risk is about to occur or has already occurred. By doing so, they can set trigger conditions that will activate the contingency plan in a timely manner, allowing the team to respond to risks effectively. Some examples of symptoms that could indicate a risk is about to occur or has already occurred include delays in material delivery, changes in building codes, and unexpected weather conditions, as mentioned in the scenario. By identifying these symptoms, the team can set trigger conditions that will activate the contingency plan if these symptoms are observed. 18 / 50 The project team is implementing a computer interface to facilitate communications between two ticketing systems for two major companies in the IT industry. While planning risk responses, the project team agrees on a contingency plan that should mitigate the negative impact of the risk. However, during project execution, one of the subject matter experts identified a residual risk that was not considered during the risk response planning session that could potentially affect the project schedule baseline. What should the risk manager do to handle this residual risk? Analyze this risk and update the risk register. Increase the management reserve. Accept the risk because it is minor. Reject the risk since the risk plan is finished. When a residual risk is identified during project execution that was not considered during the risk response planning session, the risk manager should analyze the risk and update the risk register. This is because the risk response plan may need to be adjusted to address the new risk, and the risk register should be updated to reflect the new information. 19 / 50 A risk manager is managing the build of an off-shore data center and is the custodian of the assets procured by the project. The risk manager is informed by a team member that an asset was lost, and the team member is ready to pay for the missing asset. How should the project manager handle this situation? Reprimand the team member, order that they cover the cost of the missing asset, and update the asset register. Disclose the situation to the customer, purchase the replacement asset, and update the asset and risk register. Notify management, replace the asset with the help of an insurance representative, and update the asset register. Inform the customer and management, launch an investigation, take corrective action, and update the risk register. The risk manager should immediately communicate the incident and any resulting actions to relevant stakeholders, including the customer and the manager. The risk manager should investigate the situation to determine the cause of the loss and assess the impact on the project. Without an investigation, it may be difficult to accurately identify where the failures were, who is responsible, how to respond, and how to prevent this from happening again. Based on the investigation, the risk manager should determine the appropriate response to the situation and take corrective action. The risk manager should document the incident in the risk register and other relevant project documents to ensure that it is properly tracked and managed. By following these steps, the risk manager can effectively manage the situation and minimize its impact on the project. 20 / 50 A new project is initiated to develop several new financial products and services for a company with offices in several countries. The risk manager has researched the regulations for each of the countries. Based on the research, the risk manager is concerned that some new products and services do not offer enough protection for the consumer. What should the risk manager do first? Identify all of the project risks. Quantify the project risks. Develop a risk response strategy. Perform scheduled risk audits. The first step is to identify the risks, which is the process of determining and documenting the risks that might affect the intended outcomes. Regulations are requirements imposed by a governmental body. These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance. The risk manager has to account for the regulations of each country and identify the risks associated with those regulations. 21 / 50 While performing a qualitative project risk analysis process the risk manager finds that the product is missing the “Definition of Done”. What type of risk is this? Commercial risk External risk Management risk Technical risk Definition of Done (DoD) is a checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use. The DoD is a critical component of the product development process, and its absence can lead to technical issues and challenges in the project. The risk manager should address this risk by identifying and analyzing potential impacts and developing appropriate risk responses to mitigate or avoid the risk. 22 / 50 A six-month, US$1.2 million project is two months into implementation. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project’s reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones. Based on this project data, what technique should the risk manager recommend to improve the risk management process? Increase the risk manager's position to a full-time position and acquire a dedicated project schedule lead. Adjust project risk thresholds to increase the number of residual risks on the project. Increase the frequency of risk status meetings and update the risk management plan. Perform a variance analysis and potentially allocate more reserves to improve risk mitigation. The risk manager should recommend performing a variance analysis and potentially allocating more reserves to improve risk mitigation. This will help to identify the root causes of the missed risk mitigation milestones and determine if additional resources or funding are needed to address the risks. The monthly risk management reviews established by the risk manager will also help to monitor the effectiveness of the risk management process and make any necessary adjustments. 23 / 50 A technology project has members of a project team from multiple countries. The stakeholders have stated that this arrangement will keep the project within budget. However, the risk manager believes that the stakeholders have not accounted for issues that might arise that could affect the success of the project. What should the risk manager do to record this concern? Document the risks in the risk register. Revise the stakeholder engagement plan. Capture the information in the issues log. Update the resource management plan. Having a dispersed project team does not come without risks. These risks need to be identified and documented in the risk register for the project. A risk register is a repository in which outputs of risk management processes are recorded. Information in a risk register can include the person responsible for managing the risk, probability, impact, risk score, planned risk responses, and other information used to get a high-level understanding of individual risks. 24 / 50 The project manager requests a method to analyze risk data in a simple format. What format should the risk manager suggest for the preliminary review of the data? Monte Carlo analysis Fishbone diagram Latin Hypercube analysis Data tables When analyzing risk data in a simple format, a data table is a suitable format for the preliminary review of the data. A data table provides a clear and concise way to organize and present the risk data, making it easy to review and analyze. Additionally, a data table can be customized to include specific information relevant to the project, such as risk category, current risk status, causes, effects on objectives, risk triggers, and timing information. 25 / 50 Question A new team member is added to the project team from a matrix organization. The project is unique within the organization and has a high level of risk associated with it. How should the project’s risk manager familiarize the new team member with the project’s risk management process? Request that the functional manager confirm that the resource is proficient in risk management. Provide training on the risk management tools and techniques being used on the project. Tell the new team member to review the risk management plan and ask team members if they need help. Give the new team member a copy of the risk register and the latest project status report. This can include identifying gaps in knowledge and skills as well as strategies to address those gaps through training, mentoring, or coaching. Providing training on the risk management tools and techniques being used on the project can help ensure that the new team member understands the process and is able to contribute effectively to the project’s risk management efforts. This can help minimize the impact of risks on the project and ensure its success. The risk manager should also mentor any new resource to ensure that the risk management process is fully understood and applied. 26 / 50 A risk manager and the project team identified risks, performed a qualitative risk analysis, and prepared a risk response plan. However, delays in the response to risk events are affecting the project schedule. How would assigning risk owners to the risk responses help avoid these delays? Risk owners work with the project sponsor to ensure the risk response plan will be effective. Risk owners identify likely constraints and assumptions before the risk events occur. Risk owners are responsible for implementing the appropriate risk response strategy. The risk report assigns responsibility for delays in the project schedule to the appropriate risk owner. Risk owners are responsible for implementing the appropriate risk response strategy, which means they are accountable for taking action to address the identified risks. Risk owners for each risk are nominated as part of the risk identification process and confirmed while performing qualitative risk analysis. If a risk owner is not assigned to a risk, then the risk response will not be implemented in a timely manner and delays to the schedule could occur. 27 / 50 Question A project manager is preparing for a meeting with the chief executive officer (CEO) to present the project’s master schedule of the critical path. One hour before the meeting, the project manager receives a report from an off-shore team documenting newly identified significant risks associated with a critical milestone in the development and quality testing standards of off-shore production activities. Based on this information, the project manager realizes the master schedule is no longer realistic. What should the project manager do? Converse with the stakeholders before the meeting to discuss the report and request their opinion on how to proceed. Present the current master schedule to the CEO and inform them that it will be subject to change in the coming weeks. Ask to reschedule the meeting communicating that newly identified risks will impact the schedule and must be assessed. Present the existing schedule as planned and wait to inform the CEO of the new risks until after they have been evaluated. In the given scenario, the project manager should ask to reschedule the meeting and communicate that newly identified risks will impact the schedule and must be assessed. It is important to inform the CEO that newly identified risks have rendered the current master schedule obsolete and it must be reassessed. By rescheduling the meeting and communicating the situation to the CEO, the project manager can assess the new risks, update the schedule, and present a more accurate representation of the project timeline. This will allow the CEO to make informed decisions and adjust expectations accordingly. 28 / 50 During a retrospective meeting, the project team confirmed that all deliverables were completed according to the specifications provided in the product backlog. However, the number of errors found during testing increased dramatically. What should the project manager do? Meet with quality assurance specialists to clarify the issue and seek resolutions. Review the risk management plan to determine the proper mitigation strategy. Perform a Monte Carlo analysis to identify possible scenarios and actions. Document the risk in the risk register and monitor it during the next iteration. The number of errors found during testing increased dramatically indicating that there is a quality issue with the deliverables. The project manager should meet with the quality assurance specialists to resolve these issues. This can help identify the root cause of the issue and develop appropriate solutions to address it. 29 / 50 During a project review meeting, an executive scrutinizes the risk section, including risks on the watch list, and demands action to close them out. What is the executive’s risk attitude? Averse Seeking Neutral Tolerant The executive’s risk attitude is risk-averse, as evidenced by their demand to close out risks on the watch list. Risk-averse individuals and organizations tend to be more cautious and conservative in their approach to risk management and may prioritize risk mitigation and avoidance over risk-taking. It is important for project teams to understand the risk attitudes of stakeholders and to tailor their risk management approach accordingly. 30 / 50 During the construction of an infrastructure improvement project, several risks have materialized and require immediate mitigation efforts. To optimize response effectiveness, the risk manager wants to leverage monitoring processes to gather data about these active risks. Which of the following actions would be relevant and valuable in leveraging monitoring processes to gather data about these active risks? Risk analysis and performance report preparation. Ongoing risk response analysis and risk audits. Continuous retrospectives and risk register review. Regularly surveying the team's risk perceptions. To support the response to realized risks, ongoing risk response analysis and risk audits would be most relevant and valuable in leveraging monitoring processes to gather data about these active risks. This process helps in identifying any gaps or areas for improvement in responding to the realized risks. Risk response analysis involves reviewing the effectiveness of the risk response strategies that have been implemented and making adjustments as necessary. Risk audits involve reviewing the risk management processes and procedures to ensure that they are being followed and are effective. 31 / 50 During a status meeting, a team member alerts the project manager that the delivery timeline for a component prototype is unattainable due to the unanticipated complexity of the requirements. After confirming the impending delay, the project manager must take action to address the situation. How should the project manager address this issue? Identify the extent to which the complexity will impact the rest of the project. Delegate prototype development activities to a more experienced team member. Allocate additional funding to the development budget to expedite delivery. Assign additional resources to prototype development and proceed as planned. The project manager should identify the extent to which the complexity will impact the rest of the project. This can help the project manager determine the best course of action to address the situation and minimize the impact of the delay on the project. 32 / 50 Which of the following techniques for planning risk response can provide a means of identifying symptoms for use as trigger conditions for contingency responses? Root cause analysis Quantitative risk analysis Value stream mapping Earned value analysis Root cause analysis can provide a means of identifying symptoms for use as trigger conditions for contingency responses. By identifying the root cause of a risk, the project team can develop response plans to proactively address negative product risks or take advantage of potential opportunities. This approach can help to identify symptoms and warning signs that can be used as trigger conditions for contingency responses. 33 / 50 A project manager wants to represent the distribution of uncertainty around a risk model element. However, good data on the variability of the risk model element has not been collected and only contains minimum and maximum values. What curve should the project manager use to represent the distribution? Uniform Beta Normal Lognormal When representing the distribution of uncertainty around a risk model element with only minimum and maximum values available, the project manager should use a uniform distribution. A uniform distribution assumes that all values within the minimum and maximum range are equally likely to occur. This is appropriate when there is no additional information available about the distribution of the variable. 34 / 50 A risk manager is working on a new project for which historical data is not available. The risk manager planned to use historical data to identify potential risks and develop appropriate risk response strategies. What should the project manager do next? Ignore the missing historical data and continue developing risk response strategies. Identify risks based on the information available and allocate additional contingency reserves. Develop a protocol for capturing historical data and documenting it in a lessons learned register. Develop a risk management plan based on expert judgment and other available information. The fitting approach for the risk manager to take is to develop a risk management plan based on expert judgment and other available information. Expert judgment can offer insight based on expertise in a subject area, industry segment, organizational processes, etc. The risk manager should work closely with the project team, experts, and other stakeholders to ensure that all potential risks are identified and appropriate risk response strategies are developed and implemented. By taking a proactive approach to risk management, the risk manager can help minimize the impact of potential risks on the project and increase the likelihood of project success. 35 / 50 The opening of a new overseas office faces potential delays as the required permit has not yet been issued by the local government. The project team met to evaluate the appropriate course of action as outlined in the risk register. After a thorough assessment, the team decided to postpone the opening to another date. Which document should the project manager use to update the project management plan? Risk management plan Risk report Risk register Lessons learned register The project manager should use the risk register to update the project management plan. The risk register contains information about identified risks, their likelihood and impact, and the risk response strategies that have been developed to address them. By updating the project management plan with information from the risk register, the project manager can ensure that the project team is aware of the potential delays and the actions that have been taken to address them. This can help to minimize the impact of the delays on the project and ensure its success. 36 / 50 While reviewing preliminary project information the project manager discovers that, based on the organizational business drivers, there is an opportunity to increase the value of the project outcome. In order to exploit this opportunity the organization must invest in a new technology. How should the project manager justify this investment when presenting this information to senior management? Using the new technology will help to ensure that the opportunity is realized. The product will be obsolete if the organization does not invest in the technology. The project team should be empowered to make value-delivery decisions. Creating the best possible product should be the sole focus of all projects. The project manager should explain how the new technology will help to exploit the opportunity and increase the business value of the project. Exploiting an opportunity involves taking focused action to capture the positive effect. In this case, exploiting the opportunity requires the focused action of investing in a new technology. The project manager should also describe how the technology can contribute to achieving the future project goals and objectives. It is important to help senior leadership make informed decisions by articulating the impact of project management technology adoption on achieving organizational goals and increasing business value. 37 / 50 A risk manager is planning for a new project but is running into resistance while attempting to manage stakeholder expectations. One key stakeholder is refusing to acknowledge the reality of several project risks and requests that the risk manager disregard those risks. What should the risk manager do? Organize a conflict management conference to address the stakeholder's resistance. Explain the consequences of ignoring the specific risks and describe the potential impacts. Remove the risks from the risk management documents as requested by the stakeholder. Prepare a report for senior management documenting the issue and requesting support. The risk manager should explain the consequences of ignoring the identified risks and provide options for addressing them. The stakeholder may be reluctant because they are only considering factors that impact them and may not have a full understanding of the project environment. The risk manager should seek to establish a shared understanding through effective communication, mentoring, and transparency. This can help to establish a positive working relationship, foster collaboration, and proactively manage stakeholder expectations. 38 / 50 A project manager is assigned to a two-month project with three project team members. The project sponsor tells the project manager to skip any risk planning activities because risk management is not necessary for such a small project. How should the project manager respond? Explain that even small projects can encounter risks that could have a significant impact on the project. Accept the project sponsor's decision to skip risk planning activities and initiate the project. Conduct risk planning activities because the sponsor does not understand risk management. Escalate the issue to the PMO and request permission to conduct risk management activities. The project manager should respond by explaining to the project sponsor that even small projects can encounter risks that could have a significant impact on the project. By identifying and managing these risks, the project team can increase the likelihood of project success. It is important for the project manager to communicate the importance of risk management and the potential benefits it can bring to the project. 39 / 50 An organization has a low threshold for risk and is concerned about initiating a project that has an elevated level of uncertainty associated with the local economy. All other identified risks are within the organization’s risk tolerance parameters. Management would like to initiate the project but before moving forward they require a better understanding of the risks and how they contribute to overall project risk. The project manager is creating a report to present to senior management in order to determine whether or not the project should be initiated. What should the project manager do to provide additional clarity and facilitate informed decision-making? Facilitate conflict resolution to reduce friction among stakeholders. Prioritize the risks based on their severity and likelihood of occurrence. Create a new project proposal with a downsized scope to reduce risk. Advise that the project be postponed based on the current uncertainty. The most appropriate way for the project manager to provide additional clarity and facilitate informed decision-making is to prioritize the risks based on their severity and likelihood of occurrence. Presenting a visual representation of project risks can aid in decision-making and prioritization. This will help senior management understand the potential impact of the risks and make informed decisions about whether or not to proceed with the project. It’s important for the project manager to communicate the prioritized risks and their potential impact to senior management in a clear and concise manner, and to provide recommendations for risk management strategies that can mitigate or avoid the highest priority risks. This will help ensure that the project is aligned with the organization’s risk tolerance and overall objectives. 40 / 50 At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project. What risk management process improvement should the risk manager recommend for future similar projects? Increase the frequency of risk management meetings with the project manager. Revise the processes to increase the level of accuracy of probability and impact scores. Document the risk audit report and capture it in the lessons learned database. Expand the implementation of risk identification techniques and involve all stakeholders. The risk manager should recommend revising the level of accuracy of probability and impact scores for future similar projects. This will help to ensure that the identified risks are more accurately assessed and that appropriate risk response strategies are developed and implemented. The risk manager should also consider updating the risk management plan and engaging with stakeholders to gather their input and feedback on the risk management process. 41 / 50 A risk manager is presenting the risk management plan for a high-priority project to senior management and organizational executives. The project is cutting-edge and part of a completely new strategy for the organization. A majority of the management team is excited about the potential opportunities that the project presents, but some high-priority leadership team members are not comfortable taking on the risk and expense associated with the project. During the presentation, it was clear the groups of stakeholders did not agree on the appropriate organizational risk appetite which has led to conflict. How can the risk manager lead conflict resolutions between stakeholders in agreeing on risk appetite? Remind everyone that the project has been approved and planning has already begun so it cannot be altered or revised at this stage. Agree with the stakeholders that have the highest risk appetite in order to get more buy-in and have the opportunity to experiment. Cancel or postpone the project and focus on projects that are less risky and have less expense associated with project execution. Facilitate discussions and negotiations between stakeholders to reach a consensus on the appropriate level of risk appetite for the project. The risk manager should facilitate discussions and negotiations between stakeholders to reach a consensus on the appropriate level of risk appetite for the project. By considering factors such as the organization’s and stakeholders’ risk attitude, potential benefits and threats to the organization’s and stakeholders’ businesses, and shared and conflicting objectives, the risk manager can help resolve conflicts related to risk appetite and ensure that all stakeholders are aligned on the appropriate level of risk for the project. When senior managers suffer conflict, neutral facilitation typically helps more than detailed recommendations. 42 / 50 A project team must incorporate newly identified risks into the risk management framework. Stakeholders would like an update on which risks would have the highest impact on the project. What should the project team do? Perform an assumptions analysis Perform a sensitivity analysis. Perform a root cause analysis. Perform a variance analysis. A sensitivity analysis is a quantitative risk analysis method that determines which uncertainty has the greatest potential for an impact. Sensitivity analysis is used to determine which risks have the greatest potential impact on a project by analyzing the effect of individual project risks on the overall project outcome. It involves varying the values of individual project risks to see how they affect the project outcome. By using a sensitivity analysis, the team can identify which risks have the greatest potential impact on the project and prioritize them accordingly. 43 / 50 A project manager identifies a risk in a multifunctional project and decides to take no action to address it. What should the risk manager do if the risk occurs and has a negative impact on the project? Escalate the issue to the sponsor. Initiate a formal change request. Implement a contingency plan. Review the project management plan. If a risk occurs and the project manager has decided to take no action, the risk manager should implement a contingency or fallback plan. This plan should have been developed and implemented as part of the risk management process and should be triggered when the risk occurs. The contingency plan should include specific actions to be taken to mitigate the impact of the risk and should be regularly reviewed and updated as necessary. 44 / 50 A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project. What is the most effective method to capture these opportunities? Include them in the lessons learned. Schedule a project team meeting. Notify the project stakeholders. Establish a contingency reserve. The most effective method to capture opportunities identified through quantitative risk analysis is to establish a contingency reserve. A contingency reserve can help plan for opportunities by providing a source of funding or resources to take advantage of the opportunity if it occurs. By having a contingency reserve in place, the project team can be better prepared to respond to unexpected events and take advantage of opportunities. 45 / 50 Question A risk manager on a large-scale development project has established detailed risk management procedures. The risk manager wants to ensure their effectiveness and is refining the risk monitoring practices to better track, record, and assess execution success. What metric would be most valuable to track and record the execution quality of risk-related procedures? The degree of variation from the established risk response strategy. The number of risks that were identified and successfully mitigated. The impact of realized risks on the project objectives and baselines. The level of stakeholder satisfaction with the risk-related procedures. The number of risks that were identified and successfully mitigated is the most valuable metric to track and record the execution quality of risk-related procedures. This metric provides insight into the effectiveness of the risk management procedures and the ability of the project team to identify and respond to potential risks. By tracking this metric, the risk manager can identify areas for improvement and refine the risk management procedures to better address potential risks. 46 / 50 After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget. What forecasting methodology should the project manager request be utilized to calculate the impact? Estimate to complete (ETC) Budget at completion (BAC) Estimate risk completion (ERC) Estimate at completion (EAC) EAC is a forecasting technique used to estimate the total cost of completing a project based on the project’s past performance and current performance. It takes into account the actual costs incurred to date, the budgeted cost for the remaining work, and the budgeted cost for any new work that may be required. EAC is calculated by adding the actual costs incurred to date to the estimated cost of the remaining work, which is based on the original budgeted cost for the remaining work and adjusted for any changes in scope or assumptions. EAC can be calculated using several different formulas, including the following: 47 / 50 Question A risk manager is working with an experienced project team on a complex project. During production, a risk materializes and the team meets to discuss the implementation of the appropriate risk response strategy. Despite planning risk responses as a team, the risk manager notices that many of the team members seem extremely uncomfortable and are reluctant to implement the risk response. What should the risk manager have done in order to better understand how the team would react in this situation? Identified the team's risk attitude. Devised a more precise response plan. Explained that the project is risky. Requested a more adaptable team. The risk manager should have identified the team’s risk attitude in order to better understand how they would react in a situation where a risk materialized. By identifying the team’s risk attitude, the risk manager can better understand how they are likely to respond to future risks and can adjust their risk management strategy accordingly. This will help to promote transparency and ensure that the team is comfortable with the chosen risk response. In this case, it seems that the team is more risk averse than the risk manager may have assumed. 48 / 50 Question A project team is working on a critical project and one of the identified risks is approaching its risk threshold. This risk introduces potential delays due to unexpected changes in requirements. Who is ultimately responsible for monitoring the risk that is about to exceed its risk threshold? All project stakeholders The customer Senior management The risk owner The risk owner is ultimately responsible for monitoring the risk that is about to exceed its risk threshold. The risk owner is the individual responsible for selecting and implementing an appropriate risk response strategy and managing the corresponding risk throughout the subsequent risk management processes. It is also the responsibility of the risk owner to immediately report any changes in the risk trigger status and to drive the defined countermeasures. The original project manager should have identified high-level risks and risk responses in the project planning phase. Identifying high-level risks and responses in the project planning phase can help to ensure that potential risks are identified and addressed before they become issues. This can help to mitigate risks and ensure that appropriate risk response strategies are in place to address any issues that may arise. 49 / 50 A project manager has just taken over an ongoing project from another project manager. During a review of the project management plan, the new project manager realizes that the cost variance and schedule variance are largely negative. Several reported issues have not been resolved, vendors have not been paid for work done, and risk mitigation is quickly depleting the budget. Which action should the original project manager have taken to avoid this situation? Identified appropriate and comprehensive project handoff procedures. Added a substantial contingency reserve budget to the project charter. Identified high-level risks and responses in the project planning phase. Ensured that governance controls were approved and implemented. 50 / 50 A risk manager has finished a qualitative risk analysis with their team. The risk manager asked the team to update the relevant documents, but they only updated the risk register, issue log, and risk report. Which project document still needs to be updated based on this information? The lessons learned register The change log The assumption log The project charter At a minimum, the risk register, issue log, assumption log, and risk report should be reviewed for revision upon completion of the qualitative risk analysis. The assumption log is a document that records all the assumptions made during the project planning phase and is used to track and manage changes to those assumptions throughout the project. By updating the assumption log, the risk manager can ensure that all assumptions related to identified risks are up-to-date and that appropriate risk response strategies are in place. Your score is 0% For more Sample papers, refer the links below: RMP Exam 1