PRINCE2 - 7 Sample Paper 4

PRINCE2 - 7 Sample Paper 4

1 / 60

Which principle is being applied when reviewing whether the project will deliver valuable products?

2 / 60

Which characteristic of a project relates to teams from different organizations working together?

3 / 60

Which is a delivery approach that is defined as starting the next delivery step only when the previous step has been completed and the product is made available at the end of project?

4 / 60

What is the definition of a project outcome in PRINCE2?

5 / 60

Which product demonstrates continued business justification?

6 / 60

Which is NOT a purpose of a Benefits Review Plan?

7 / 60

An off-specification is classified as:

8 / 60

Which is a recognized issue type in PRINCE2?

9 / 60

What else is part of configuration management?

10 / 60

Which is a core activity within configuration management?

11 / 60

What is essential for effective issue and change control?

12 / 60

Which of the following is typically funded from the change budget?

13 / 60

What type of activity should be funded from the change budget?

14 / 60

Which is NOT a function of the Issue Register?

15 / 60

If the Project Board approves a Request for Change, where is this recorded?

16 / 60

The Change theme’s primary purpose is to:

17 / 60

During the issue procedure, which step involves analyzing possible responses?

18 / 60

If a deliverable cannot meet its baseline requirements, what is the first step?

19 / 60

Which statements about Closing a Project are true?

  1. It provides a fixed point to receive final Work Packages.
  2. It confirms whether project objectives have been achieved.

20 / 60

During Closing a Project, what critical activity takes place?

21 / 60

One objective of Closing a Project is to:

22 / 60

Who is responsible for producing the Benefits Management Approach?

23 / 60

What is the main role of the Project Board?

24 / 60

Which PRINCE2 principle requires continuous assessment of project justification?

25 / 60

What is considered the baseline plan that guides the overall project management?

26 / 60

What is the purpose of the Daily Log?

27 / 60

What happens during the 'Controlling a Stage' process?

28 / 60

What is considered a quality method in PRINCE2?

29 / 60

What is the main output of the 'Starting Up a Project' process?

30 / 60

Who has the authority to formally initiate the project?

31 / 60

Which product provides the Project Board with summarized progress information?

32 / 60

What is the key purpose of the 'Managing a Stage Boundary' process?

33 / 60

Who defines the quality criteria and verifies that product quality is met?

34 / 60

What is the purpose of a Configuration Item Record?

35 / 60

Who is responsible for preparing the Team Plan?

36 / 60

What is the primary purpose of the Project Plan?

37 / 60

What does ‘off-specification’ mean in PRINCE2 terms?

38 / 60

Which product serves to log all project issues such as problems, change requests, and off-specifications?

39 / 60

When is the Business Case reviewed during a PRINCE2 project?

40 / 60

What is the central purpose of maintaining a Business Case throughout a PRINCE2 project?

41 / 60

In which product are all risks categorized, assigned owners, and monitored during the project lifecycle?

42 / 60

What is the first activity in the PRINCE2 risk management procedure?

43 / 60

What document holds all identified threats, opportunities, responses, and current status throughout the project?

44 / 60

Which management product outlines stakeholder interests, their information needs, and how engagement is maintained?

45 / 60

Which theme ensures the project remains within time, cost, and scope tolerances and facilitates escalation if breached?

46 / 60

In PRINCE2, which product defines the timing, ownership, and methods for post-project benefit evaluations?

47 / 60

What practice defines how the project handles off-specifications, requests for change, and problem concerns?

48 / 60

In PRINCE2, which practice governs the criteria and review methods for verifying that a product is fit for use?

49 / 60

Which process delivers the Lessons Report and formally closes the project?

50 / 60

What is the purpose of the Starting Up a Project process?

51 / 60

Which process authorizes delivery of Work Packages and monitors daily execution?

52 / 60

Which process formally authorizes project initiation?

53 / 60

Which process is triggered when performance deviates beyond tolerances?

54 / 60

What is the primary output of the Managing a Stage Boundary process?

55 / 60

Who is responsible for producing the Checkpoint Report?

56 / 60

Which role ensures independent oversight of governance, quality, and risk?

57 / 60

Which role is responsible for representing the users and defining acceptance criteria?

58 / 60

Who holds ultimate accountability for the justification of the project?

59 / 60

Which principle underlines that authority and accountability must be explicitly defined?

60 / 60

Which PRINCE2 principle ensures the method is adjusted to match the size, complexity, and risk of the project?

Your score is

0%

The ITIL, Prince2, and PeopleCert Scrum courses are provided by PMOBytes Consultation and Training, an ATO/Affiliate of PeopleCert. ITIL™, PRINCE2™, and PeopleCert Scrum are a trademark of the PeopleCert group. Used under license from PeopleCert. All rights reserved. The MSP, ITIL4 Specialist CDS, Prince2 Agile, and PeopleCert DevOps courses are provided by Ducis Group, an ATO/Affiliate of PeopleCert. MSP, ITIL, PRINCE2 , PRINCE2 Agile, and PeopleCert DevOps are registered trade marks of PeopleCert group. Used under licence from PeopleCert. All rights reserved.
Chat on WhatsApp