PRINCE2 - 7 Sample Paper 4

PRINCE2 - 7 Sample Paper 4

1 / 60

Which principle is being applied when reviewing whether the project will deliver valuable products?

2 / 60

Which characteristic of a project relates to teams from different organizations working together?

3 / 60

Which is a delivery approach that is defined as starting the next delivery step only when the previous step has been completed and the product is made available at the end of project?

4 / 60

What is the definition of a project outcome in PRINCE2?

5 / 60

Which product demonstrates continued business justification?

6 / 60

Which is NOT a purpose of a Benefits Review Plan?

7 / 60

An off-specification is classified as:

8 / 60

Which is a recognized issue type in PRINCE2?

9 / 60

What else is part of configuration management?

10 / 60

Which is a core activity within configuration management?

11 / 60

What is essential for effective issue and change control?

12 / 60

Which of the following is typically funded from the change budget?

13 / 60

What type of activity should be funded from the change budget?

14 / 60

Which is NOT a function of the Issue Register?

15 / 60

If the Project Board approves a Request for Change, where is this recorded?

16 / 60

The Change theme’s primary purpose is to:

17 / 60

During the issue procedure, which step involves analyzing possible responses?

18 / 60

If a deliverable cannot meet its baseline requirements, what is the first step?

19 / 60

Which statements about Closing a Project are true?

  1. It provides a fixed point to receive final Work Packages.
  2. It confirms whether project objectives have been achieved.

20 / 60

During Closing a Project, what critical activity takes place?

21 / 60

One objective of Closing a Project is to:

22 / 60

Who is responsible for producing the Benefits Management Approach?

23 / 60

What is the main role of the Project Board?

24 / 60

Which PRINCE2 principle requires continuous assessment of project justification?

25 / 60

What is considered the baseline plan that guides the overall project management?

26 / 60

What is the purpose of the Daily Log?

27 / 60

What happens during the 'Controlling a Stage' process?

28 / 60

What is considered a quality method in PRINCE2?

29 / 60

What is the main output of the 'Starting Up a Project' process?

30 / 60

Who has the authority to formally initiate the project?

31 / 60

Which product provides the Project Board with summarized progress information?

32 / 60

What is the key purpose of the 'Managing a Stage Boundary' process?

33 / 60

Who defines the quality criteria and verifies that product quality is met?

34 / 60

What is the purpose of a Configuration Item Record?

35 / 60

Who is responsible for preparing the Team Plan?

36 / 60

What is the primary purpose of the Project Plan?

37 / 60

What does ‘off-specification’ mean in PRINCE2 terms?

38 / 60

Which product serves to log all project issues such as problems, change requests, and off-specifications?

39 / 60

When is the Business Case reviewed during a PRINCE2 project?

40 / 60

What is the central purpose of maintaining a Business Case throughout a PRINCE2 project?

41 / 60

In which product are all risks categorized, assigned owners, and monitored during the project lifecycle?

42 / 60

What is the first activity in the PRINCE2 risk management procedure?

43 / 60

What document holds all identified threats, opportunities, responses, and current status throughout the project?

44 / 60

Which management product outlines stakeholder interests, their information needs, and how engagement is maintained?

45 / 60

Which theme ensures the project remains within time, cost, and scope tolerances and facilitates escalation if breached?

46 / 60

In PRINCE2, which product defines the timing, ownership, and methods for post-project benefit evaluations?

47 / 60

What practice defines how the project handles off-specifications, requests for change, and problem concerns?

48 / 60

In PRINCE2, which practice governs the criteria and review methods for verifying that a product is fit for use?

49 / 60

Which process delivers the Lessons Report and formally closes the project?

50 / 60

What is the purpose of the Starting Up a Project process?

51 / 60

Which process authorizes delivery of Work Packages and monitors daily execution?

52 / 60

Which process formally authorizes project initiation?

53 / 60

Which process is triggered when performance deviates beyond tolerances?

54 / 60

What is the primary output of the Managing a Stage Boundary process?

55 / 60

Who is responsible for producing the Checkpoint Report?

56 / 60

Which role ensures independent oversight of governance, quality, and risk?

57 / 60

Which role is responsible for representing the users and defining acceptance criteria?

58 / 60

Who holds ultimate accountability for the justification of the project?

59 / 60

Which principle underlines that authority and accountability must be explicitly defined?

60 / 60

Which PRINCE2 principle ensures the method is adjusted to match the size, complexity, and risk of the project?

Your score is

0%