RMP Sample Exam 1

RMP Sample Exam 1

1 / 50

During a project review meeting the risk manager asks the team for updates on closed risks from the previous period and finds that they do not have a comprehensive understanding of the original trigger conditions.

What should the risk manager do to address this?

2 / 50

During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. The project manager reviews the risk management plan and discovers risk categories largely focused on technical and customer-related risks, not internal issues. The project still has several months before completion and the project manager wants to revise the risk management plan to account for internal risk areas.

Who should the project manager collaborate with to revise the risk management plan at this stage of the project?

3 / 50

A junior risk manager approaches a senior risk manager seeking advice on an analysis method to enhance sample representativeness and improve simulation accuracy. The senior risk manager says that an analysis method that uses stratified sampling without replacement would be best.

Which analysis method should the senior risk manager suggest?

4 / 50

A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks.

What risk-related information should be included in the monthly status meeting of this complex project?

5 / 50

A project team is planning for the construction of a major housing development. The development will consist of five stand-alone apartment buildings. The project team is in the process of identifying project risks. Many key construction activities will be completed by a contractor. The project manager intends to include the contractor in risk identification exercises, but one key stakeholder voices concerns and would like to identify risks internally.

How should the project manager address this concern?

6 / 50

A project manager is working with the project team to prioritize identified project risks, but several stakeholders are interfering with the process. The stakeholders have competing priorities and are attempting to influence the prioritization process to favor their priorities.

What should the project manager do in order to ensure that the team prioritizes risks appropriately?

7 / 50

A risk manager is working on a complex project that is running over budget and over schedule. Some stakeholders believe that these overages are a result of poor risk planning techniques.

What can the risk manager do to determine the validity of these concerns?

8 / 50

When using the risk register to manage the cost risk analysis, which of the following techniques models the way correlation arises, and avoids the need to estimate the correlation coefficients?

9 / 50

Despite the project team carrying out risk management processes and adhering to organizational risk planning procedures, the contingency reserves for a recent project were depleted before the project was completed.

What recommendation could be implemented to prevent this from recurring?

10 / 50

Mid-project, a risk manager goes on medical leave and is replaced by a new risk manager. Before leaving, the original risk manager met with the new risk manager to thoroughly review and discuss the project and the risk management plan. During a status meeting, the new risk manager is notified that a known risk has materialized.

What is the appropriate course of action in this case?

11 / 50

Due to budget constraints, the project team decides to use low-cost equipment with high testing uncertainty. This has led to discrepancies and wasted resources. A team member suggests using high-quality equipment with lower test uncertainty to improve testing quality. The team member states that the high-quality equipment will cost more, but the increased testing quality would reduce waste, decrease risks, and lower overall costs.

How should the project risk manager respond to this proposal?

12 / 50

It was discovered that the likelihood of several project risks was overestimated during the risk identification process. This discrepancy can be attributed to the influence of bias while identifying risks.

What could the project manager have done to avoid this situation?

13 / 50

During a weekly project review meeting, a stakeholder identifies some new risks. When creating risk responses for these newly identified risks, what should the project team do to discover trends and more efficiently manage the responses?

 

14 / 50

A project team member identifies, but does not document, a risk early in the project, because it is considered to be insignificant. This risk occurs later and negatively impacts the project.

What could the project manager have done differently to avoid this situation?

15 / 50

Question

During project execution a new risk is identified and the stakeholders request that the project manager take immediate steps to avoid it. However, after analysis, the project team disputes that strategy because the risk should be classified as an opportunity and suggests developing a strategy to exploit it rather than avoid it. The stakeholders disagree and state that they want all newly identified risks to be avoided whenever possible.

 

How should the project manager address this situation?

16 / 50

Question

A project manager is working with a large group of stakeholders to identify risks for a new project. Some stakeholders have been with the organization for many years, others joined only recently. The project manager noticed that the long-term stakeholders have identified very similar sets of risks whereas the newer stakeholders have longer and more varied lists.

How should the project manager address this discrepancy?

17 / 50

A project manager is conducting risk analysis for a recurring project that has been a regular undertaking for the organization. The project is a routine task focused on updating internal data systems and is repeated once a year. One of the key stakeholders is new to the organization and requests that the project team perform a quantitative risk analysis for the project.

How should the project manager respond?

18 / 50

Question

During a high-risk project, several risks have been materialized and responses have been implemented, However, the project still appears to be in trouble. The project manager is concerned that the risk management rules are not being carried out as specified.

What should the project manager do to identify the weaknesses of the risk management process?

19 / 50

Question

When analyzing the reward system in a company, there is evidence that suggests that teams are consistently dealing with major problems and operate primarily in an emergency mode. As a result, those who receive the most recognition are those developing response strategies quickly. Individuals who work efficiently and proactively are rewarded far less.

What does this observation indicate regarding the risk management process?

20 / 50

A project is in danger and the project manager realizes that this is because there is a serious misallocation of resources and the risk responses that have been implemented have been largely ineffective.

What is the most likely cause of this?

21 / 50

The risk manager is currently performing the monitoring and reporting process. Which of the following is a direct input for ongoing schedule metrics?

22 / 50

Question

A cosmetic company would like to expand into the pharmaceutical market. To assist in this, the company acquires an existing company that has established resources and experience operating in the pharmaceutical market. The new pharmaceutical products involve higher levels of governance and stricter compliance regulations. While planning for a new pharmaceutical project, the project manager realizes that the majority of stakeholders and team members have worked on cosmetic projects in the past, but only a few have experience with pharmaceutical projects.

What should the project manager emphasize when identifying risks for the project?

23 / 50

Question

During the execution of repair work, the root cause of the damage was discovered to be failures that occurred during the construction phase. The same contractor who performed the construction work is performing the repairs. Because of this, the CEO wants to negotiate with the contractor for a reduced price.

What should the project manager do?

24 / 50

The team has just completed a risk response planning session and identified responses for all the high and medium-priority risks. What should the team do with the remaining low-priority risks?

25 / 50

Question

A project has four risks that are identified during the risk identification process. The table shows the probability of each risk occurring and the corresponding cost.

 

RISK ACTIVITY PROBABILITY COST IMPACT (US$)
2 A 10% -$5,900
4 B 5% $1,000
1 C 20% -$5,000
3 D 15% $3000

What is the total estimated monetary value of the cost for this project?

26 / 50

A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead identifies the most critical information to be presented at an executive level. The information must balance communicating essential information with actions and recommendations.

What risk information should be communicated to the project sponsor?

27 / 50

Question

While planning a new project, a new project manager finds that the request for proposal (RFP) references several government regulations. However, the project manager discovers that compliance guidelines related to two specific regulations are being created and are not currently available. Senior management advises the project manager that the guidelines will be available when that stage of the project is reached and directs the project manager to continue working on the proposal.

What should the project manager do?

28 / 50

At project initiation, a quote for the required services was requested from a vendor, and the work was estimated at US$100,000. As the project progressed, requirements were updated following the company’s procurement process, and a modified quote was received for more than US$250,000. The allocated contingency funds are not sufficient to cover the difference.

What should the project manager do?

29 / 50

Question

The risk manager for a data center infrastructure project is preparing to perform a final post-project risk audit. Several stakeholders do not think that audits are valuable and are impatient with the process. They request that it be skipped in order to begin work on the next project.

How should the risk manager describe the purposes of the audit?

30 / 50

Question

A project manager is leading a project with numerous risks that may occur sequentially and could potentially result in significant financial consequences.

What should the project manager do to better understand the risks?

31 / 50

When performing integrated cost-schedule risk analysis, a risk manager must correlate the project costs and activities with the risk baseline. Why is determining correlation critical in performing this analysis?

32 / 50

Question

A risk manager is working on a deployment project to replace some equipment that will soon become obsolete. A review of the schedule and cost has revealed that the risk of a 5-month delay is likely and may introduce additional risk.

How should the risk manager address risks from the delay?

33 / 50

A race director is planning a marathon with US$80,000 in upfront costs that will be offset by race fees. The remainder of the funds will be donated to a national charity. State law mandates that all money paid by the participants must be refunded if the race is canceled for any reason.

Which of the following is the best example of a risk mitigation response?

34 / 50

A team member has a history of not meeting deadlines, but the project team does not recognize the potential impact that this could have on the project if the individual does not improve their performance.

What type of risk is this?

35 / 50

A project manager is initiating risk management planning for a project that has an elevated degree of uncertainty and risk associated with the development of the product. The project must have a clearly defined and repeatable rollout phase in order to deliver the intended business value.

What project methodology should the project manager suggest?

36 / 50

Question

A project encountered unforeseen circumstances, resulting in a higher level of risk than originally anticipated. The risk manager identified a new response strategy to address the elevated risk level more effectively, but the new strategy differs from the original plan.

What should the risk manager do?

37 / 50

Question

A project manager has been newly hired and assigned to a technology development project. As the team prepared to plan risk management for the project it became clear that siloed departments are hindering communication among cross-functional teams and making cooperation difficult. As a result, the team is having difficulty defining risk roles and responsibilities.

What should the project manager do to address this situation?

38 / 50

An organization has a new goal to become more environmentally sustainable and is planning to take incremental steps to achieve this. The organization is planning to replace the packaging for its top-selling products with sustainable alternatives. The team is preparing a SWOT analysis for this initiative.

Which of the following would be considered a strength?

39 / 50

Based on the following information, which of the following has the highest risk exposure?

Threat / Opportunity Probability Impact
Funding Shortage Very Low Very High
Materials Delivery Low High
Labor Shortage Moderate Moderate
Schedule Slippage High Low
Delayed Procurement Moderate Very High
New Technology Moderate Moderate

40 / 50

A regional vendor for custom-manufactured oil platforms is awarded a contract to design, manufacture, and install 40 offshore oil platforms. Installation of these platforms requires precision placement and stable seas to properly install the deep water structure. There are several schedule and cost incentives for early completion, and the project manager asks the project risk manager to perform an analysis evaluating the probability of meeting the incentive dates. While researching methods that could be used for performing this analysis, the risk manager realizes that there are existing spreadsheets within the organization. The risk manager is considering performing project evaluation and review technique (PERT) analysis with software owned by the organization. The other option is to buy a commercial risk analysis software suite that will perform Latin Hypercube Monte Carlo simulations for US$975.

What would be the most analytical option for this probability assessment?

41 / 50

A risk manager decided to involve a third party to manage a project risk given that they had more experience than the current project team.

What kind of response strategy did the risk manager apply to address overall project risk?

42 / 50

In a project that is critical to the organization, one of the contractors complains that approvals are lengthy and difficult to handle. The contractor mentioned this as it may impact the project schedule.

What should the risk manager do next?

43 / 50

A risk manager creates a survey for project stakeholders to obtain their opinions on high levels of risk. Key questions in the survey address acceptable levels of cost increases and schedule delays.

What is the risk manager trying to determine?

44 / 50

The risk manager for a project successfully establishes the risk management plan, creates the risk register, and performs the qualitative risk analysis with the team. As the first step of the analysis, the risk manager develops the probability and impact scales. The scales are presented to the project stakeholders, who refuse to accept the proposed scales.

What did the risk manager overlook prior to developing probability and impact scales?

45 / 50

During the execution phase of a project, a project team identifies a previously unforeseen risk that could delay the project for several months. What should the project manager do first?

46 / 50

An executive stakeholder has crucial decision power on the execution and success of a project. How should this stakeholder’s importance be reflected in the stakeholder engagement plan?

47 / 50

A project team is working to establish a radio communication system for a network of remote outposts as part of a major project designed to monitor and prevent environmental crises. The team must secure the necessary licenses to use a specific radio frequency for communications. New radio units must also be installed on each outpost, but there is a lot of uncertainty and risk associated with the installation due to weather and other environmental factors.

Which of the following project life cycles would work best for this undertaking?

48 / 50

A risk manager is notified that critical project deliverables are delayed because a key subject matter expert (SME) does not have enough time to allocate to the tasks.

 

What should the risk manager do to address this situation?

49 / 50

Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?

50 / 50

A project is behind schedule by several weeks and it is discovered that the cause of this is that there were several holidays within several months of implementation.

What should the project team have done to identify this risk and avoid this situation?

Your score is

0%