Question
A company hired a project manager to lead an adaptive project using iterative development. After a few sprints, the team feels frustrated because the client is not actively participating or helping define acceptance criteria. This lack of engagement is starting to affect morale and delivery.
What is the most likely root cause of this situation?
Solution: A. Key stakeholders are unclear about their role in an adaptive delivery model.
In adaptive (iterative or agile) environments, active stakeholder participation is essential. Stakeholders, especially the client, must provide continuous feedback, help define acceptance criteria, and collaborate closely with the delivery team. If they don’t understand this role, they tend to disengage, which leads to team frustration, unclear priorities, and slow or misaligned progress. This is the root cause of the situation described in the scenario.
All other options are incorrect.
The delivery team lacks sufficient experience with iterative development methods. This might affect delivery quality, but it doesn’t explain the client’s lack of participation or the missing acceptance criteria. The core issue is about stakeholder behavior, not team skills.
The sponsor wants results but is detached from the development process This is a symptom, not a root cause. It describes what’s happening, but not why. The sponsor may be detached because they don’t understand what’s expected of them in an adaptive setting, which is exactly what option A points to.
No working features have been shared yet for client feedback sessions While it’s true that working features can help drive feedback, adaptive frameworks don’t require a finished product to engage stakeholders. Discussions on user stories, acceptance criteria, or prototypes are enough to involve clients early. Their absence isn’t the root cause, their disengagement is.