Which plan provides the Business Case with costs during the Initiating a Project process?

2 / 30

Identify the missing word in the following sentence. The risk response type [ ? ] can be
used to respond to a threat and an opportunity

3 / 30

Which project characteristic suggests that projects should have a defined start and a defined end?

4 / 30

Used to provide a foundation for the Initiating a Project process

5 / 30

What theme estimates the cost of delivering the project?

6 / 30

Which theme addresses the need to have a strategy for communicating with stakeholders?

7 / 30

Which role is part of the project management team?

8 / 30

If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?

9 / 30

Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?

10 / 30

Which does a Project Manager produce to define and control the work to be done?

11 / 30

Which is created during the Starting up a Project process?

12 / 30

Which enables the project’s products and all interdependencies to be clearly identified and documented?

13 / 30

Which is one of the three levels of plan in PRINCE2?

14 / 30

Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project’s objectives.

15 / 30

Which product documents the information needed to demonstrate continued business justification?

16 / 30

Which is an objective of the Closing a Project process?

17 / 30

Which statement is true for ALL project stakeholders?

18 / 30

Which is NOT a PRINCE2 principle?

19 / 30

What product defines the reporting requirements between the Project Manager and Team Manager?

20 / 30

In what product should the quality criteria for a specialist product be recorded?

21 / 30

Which role is responsible for specifying the project benefits?

22 / 30

Where should an off-specification be recorded?

23 / 30

What process ensures focus on the delivery of a stage’s products and avoids uncontrolled change?

24 / 30

Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

25 / 30

What is the first task of product-based planning?

26 / 30

Where should a Team Manager look for information on the quality required for a product?

27 / 30

Which is an objective of the quality review technique?

28 / 30

How should the Team Manager report that tolerances are forecast to be exceeded?

29 / 30

Which is NOT a type of issue?

30 / 30

Which should be funded by a change budget?